One of the project setting we synchronise with Harvest when you import projects from Harvest or send project to Harvest is Project type.

We convert project types between Harvest and Price&Cost in the following way:

  • Time & Materials project in Harvest stays as Time & Materials in Price&Cost
    • We pick up Total Project Fees in Budget section in Harvest and use that as baseline budget for project in Price&Cost
    • We don't yet support Fees per Task. In this case your budget in Price&Cost will be set as 0.
    • In case you've selected No budget in Harvest - this will also result as 0 budget in Price&Cost project
    • We don't support support budgets set in hours in Harvest (i.e Total project hours, Hours per task, Hours per person)
  • Fixed Fee project in Harvest becomes Fixed Price in Price&Cost
    • We pick up Project Fees in Harvest and use that as baseline budget for project in Price&Cost
    • We don't yet support Fees per Task. In this case your budget in Price&Cost will be set as 0.
    • In case you've selected No budget in Harvest - this will also result as 0 budget in Price&Cost project
    • We don't support support budgets set in hours in Harvest (i.e Total project hours, Hours per task, Hours per person)
  • Non-Billable project in Harvest stays as Non-Billable in Price&Cost
    • We don't support support budgets set in hours in Harvest (i.e Total project hours, Hours per task, Hours per person)